Scheduling resource-constrained projects with a flexible project structure
In projects with a flexible project structure, the activities that have to be scheduled are not completely known beforehand. Instead, scheduling such a project includes the decision whether to carry out particular activities at all. This also effects precedence constraints between the finally implemented activities. However, established model formulations and solution approaches for the resource-constrained project scheduling problem (RCPSP) assume that the project structure is given in advance. In this paper, the traditional RCPSP is hence extended by a highly general model-endogenous decision on this flexible project structure. This is illustrated by the example of the aircraft turnaround process at airports. We present a genetic algorithm to solve this type of scheduling problem and evaluate it in an extensive numerical study.
- Sprache
-
Englisch
- Erschienen in
-
Series: Diskussionsbeitrag ; No. 511
- Klassifikation
-
Wirtschaft
Optimization Techniques; Programming Models; Dynamic Analysis
Operations Research; Statistical Decision Theory
Production Management
- Thema
-
Project scheduling
Genetic algorithms
RCPSP
Flexible projects
- Ereignis
-
Geistige Schöpfung
- (wer)
-
Kellenbrink, Carolin
Helber, Stefan
- Ereignis
-
Veröffentlichung
- (wer)
-
Leibniz Universität Hannover, Wirtschaftswissenschaftliche Fakultät
- (wo)
-
Hannover
- (wann)
-
2013
- Handle
- Letzte Aktualisierung
- 10.03.2025, 10:42 UTC
Datenpartner
ZBW - Deutsche Zentralbibliothek für Wirtschaftswissenschaften - Leibniz-Informationszentrum Wirtschaft. Bei Fragen zum Objekt wenden Sie sich bitte an den Datenpartner.
Objekttyp
- Arbeitspapier
Beteiligte
- Kellenbrink, Carolin
- Helber, Stefan
- Leibniz Universität Hannover, Wirtschaftswissenschaftliche Fakultät
Entstanden
- 2013