Arbeitspapier
Integrated scheduling, assembly area- and part-assignment for large scale, make-to-order assemblies
The problem of scheduling multiple, large scale, make-to-order assemblies is considered. Beside "classical" precedence- and resource constraints as known from resource constrained project scheduling we take spatial resource and part availability constraints into account. The objective is to minimize the sum of the weighted tardiness. We propose a MIP-model of the problem which is a generalization of three allocation problems. Since the problem is NP-hard, a list-scheduling heuristic is proposed and evaluated on a set of benchmark instances.
- Language
-
Englisch
- Bibliographic citation
-
Series: Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel ; No. 468
- Classification
-
Management
- Subject
-
Produktionssteuerung
Scheduling-Verfahren
Auftragsfertigung
Theorie
- Event
-
Geistige Schöpfung
- (who)
-
Kolisch, Rainer
- Event
-
Veröffentlichung
- (who)
-
Universität Kiel, Institut für Betriebswirtschaftslehre
ZBW – Leibniz Information Centre for Economics
- (where)
-
Kiel
- (when)
-
1998
- Handle
- Last update
-
10.03.2025, 11:44 AM CET
Data provider
ZBW - Deutsche Zentralbibliothek für Wirtschaftswissenschaften - Leibniz-Informationszentrum Wirtschaft. If you have any questions about the object, please contact the data provider.
Object type
- Arbeitspapier
Associated
- Kolisch, Rainer
- Universität Kiel, Institut für Betriebswirtschaftslehre
- ZBW – Leibniz Information Centre for Economics
Time of origin
- 1998